'Excessive' road cone use in Ashburton sparks cost concerns

5:40 pm today
Road cones with road workers in background.

The Ashburton District Council is defending its expenditure on safety measures for road works such as cones and fencing. Photo: 123rf / Aleksandrenko Anastasiya

Mid Canterbury farmer Ray Logan says he is fed up with the "over-the-top" use of road cones.

Driving past road works at the Ashburton Domain, where a new replacement kerb and channel was being installed, he said he could not understand why the road cones stretched the entire length of the worksite "almost touching each other".

"It's just excessive, and I see it as having no respect for the ratepayer's money," he said.

"It's already fenced on both sides, so really you only need a few dozen cones as the fence is the barricade but then you have this long line of I don't know how many road cones.

"The number of cones is completely unnecessary."

Ray Logan can't understand the "excessive use" of road cones along the kerb and channel project at the Ashburton Domain.

Ray Logan can't understand the "excessive use" of road cones along the kerb and channel project at the Ashburton Domain. Photo: JONATHAN LEASK/LDR

He said he had no problems with the work being done, as the kerb and channel needed replacing, and the health and safety aspects were part of that - "but it needs to be within reason".

Roading contractors were wasting too much money on over-the-top safety measures, especially road cones, he said.

"It certainly needs to be looked at."

Ashburton District Council contractors had been renewing the kerb and channel on Walnut Avenue, between Oak Grove and West Street/SH1 since 20 May.

Council infrastructure and open spaces group manager Neil McCann said the project costs of $180,000 included around $4000 (2.2 percent) for cones, fencing and temporary pedestrian crossings.

"Given that this work involves large heavy machinery, an open trench, and is also well used by Ashburton College, domain users and a rest home, the thorough safety measures to protect the public and the construction are appropriate and necessary."

The work was being carried out in three segments, starting at the Oak Grove end in late May.

The new kerb and channel were not as deep as the old one, but would be higher than a standard kerb to make it difficult for vehicles to be able to drive up onto the Ashburton Domain, McCann said.

Logan's observations came after Transport Minister Simeon Brown put NZ Transport Agency Waka Kotahi on notice over the cost of its traffic management.

Brown told a Budget scrutiny select committee last month it was "unacceptable" that NZTA did not know the costs of what was spent on temporary traffic management.

On top of making NZTA start to measure the costs from September, a new, less prescriptive code was coming in that should be more efficient, he told MPs.

"I've received advice that in some cases where traffic management's been proscribed, it's actually more dangerous putting out the road cones than it is actually doing the work," Brown said.

"So we actually just have to take a 'safety at a reasonable cost' approach, rather than a 'safety at any cost' approach."

A recent Waka Kotahi study found at many sites, road cones were being left out unnecessarily, frustrating motorists, he said.

"There's been an infestation."